Andreani and Others v. Italy — Italy’s capped remedy for court delays was ineffective

Case
Case of Andreani and Others v. Italy
Court
European Court of Human Rights
Date Decided
29 October 2026
Citation
ECLI:CE:ECHR:2026:1029JUD004459618
Topics
reasonable time, effective remedy, judicial delay, Pinto Act

Background

The three applications concerned Italian civil, labour, and bankruptcy-related proceedings that lasted between more than 14 years and more than 20 years. Italian courts later acknowledged that the proceedings had exceeded a reasonable time.

The applicants sought compensation under Italy’s Pinto Act. After 2012, the Act capped compensation for delay at the value of the underlying claim. Each applicant received an award at that ceiling, in amounts ranging from EUR 146.35 to EUR 4,376.71.

The Court’s Holding

The European Court of Human Rights unanimously held that Italy violated Article 6 § 1 because the underlying proceedings were excessively long. Their duration, across one to three levels of jurisdiction, was not justified.

It also held that Article 13 was violated. Although the Pinto Act formally provided compensation, the domestic courts had applied the statutory cap as if it conclusively established adequate redress. They made no genuine individual assessment of the non-pecuniary prejudice caused by the delay or of whether the award remained reasonably related to Strasbourg standards.

The Court rejected the Government’s objection that the applicants had lost victim status. The capped awards were substantially below amounts normally awarded in comparable cases and therefore did not provide appropriate and sufficient redress.

Key Takeaways

  • A domestic award for excessive delay does not remove victim status unless it provides appropriate and sufficient redress.
  • Compensation for judicial delay cannot be treated as automatically adequate merely because it equals the value of the underlying claim.
  • A remedy under Article 13 must permit a real assessment of the prejudice caused by the delay.

Why It Matters

The judgment finds that the post-2012 Pinto compensation cap, as interpreted and applied in these cases, makes Italy’s compensatory remedy ineffective for excessive-length claims. The defect was not simply the existence of a ceiling, but its use as an irrebuttable presumption that a capped award was adequate.

The ruling reinforces that domestic courts must assess delay compensation in light of the actual non-pecuniary harm and Convention standards, rather than rely mechanically on the economic value of the underlying dispute.

✉️ Get tomorrow’s cases before your first coffee
Daily Case Law is our free morning digest — the most substantive new decisions, filtered to your jurisdictions and topics, each linking back here for the full analysis.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top