Deri v. Weizmann — Supreme Court declined to bar the project company from selling apartments

Case
Liora Deri and Ariel Deri v. Zvi Weizmann and Kiryat Halav U’Dvash Ltd.
Court
Supreme Court of Israel (Israel)
Judge
עופר גרוסקופף (Israeli Judicial Selection Committee, 2018)
Date Decided
November 1, 2026
Citation
LCA 38590-10-26
Topics
Interim Injunctions; Real Estate Options; Agency; Appellate Review

Background

Kiryat Halav U’Dvash Ltd. sought financing for a Jerusalem construction project by granting lenders options to purchase apartments. In 2008, Liora and Ariel Deri paid Zvi Weizmann for an option to acquire one or more apartments totaling 125 square meters. After the project stalled, the parties entered further agreements. Their final agreement contemplated ending the relationship: Weizmann would pay the Deris NIS 1.42 million, and, once payment was completed, the Deris would have no further claims against him or anyone acting on his behalf.

Two years later, after the project’s prospects improved and other option holders reportedly received opportunities to select apartments, the Deris sued Weizmann and the company to enforce their original option. They alleged that Weizmann had acted for the company, making it directly liable. They also sought an interim injunction preventing the company from selling project apartments. The Jerusalem District Court denied interim relief against the company but restrained Weizmann from changing the status quo regarding 100 square meters of his project allocation, representing one housing unit.

The Deris sought leave to appeal only the refusal to enjoin the company. They argued that the evidence established Weizmann’s agency, that their option remained exercisable, and that an injunction would not harm the company because it had voluntarily frozen sales of 30 apartments designated for option holders. They separately sought to introduce an unredacted company letter that they said supported direct corporate liability.

The Court’s Holding

Justice Ofer Grosskopf denied leave to appeal. Appellate courts intervene in interim-relief decisions only in exceptional cases, and the Deris had not shown that this was such a case. Their application, filed roughly three months after the District Court’s ruling, also undermined the asserted urgency. Waiting for the hearing transcript did not adequately explain the delay, particularly because another month passed after they received it.

On the merits, the Court found no basis to disturb the District Court’s preliminary assessment that the claim faced obstacles, even taking the proposed new evidence into account. More importantly, the balance of convenience did not favor the Deris: they had not shown that denying an injunction against the company would cause irreparable harm incapable of monetary compensation. Their generalized concern that the company might collapse before judgment was insufficient, and the existing restraint against Weizmann reduced the risk that no apartment would remain available if their option claim ultimately succeeded.

The Court added that, because the company knew of the dispute and the injunction against Weizmann, it was expected to give the Deris advance written notice of any intended change in its relationship with Weizmann that could affect their asserted rights. The request to introduce additional evidence was denied with the appeal application, and no costs were awarded because no response had been requested.

Key Takeaways

  • Leave to appeal an interim-injunction ruling is reserved for exceptional cases, and an unexplained delay may itself demonstrate a lack of urgency.
  • A claimant seeking to restrain real-estate sales must show likely irreparable harm; a speculative fear of the defendant company’s future insolvency is insufficient.
  • A narrower injunction protecting one housing unit through the option grantor may weigh against imposing a broader restraint on the project company.

Why It Matters

The decision emphasizes that disputed agency and contractual-enforcement questions ordinarily remain for trial when interim protection can be assessed through the balance of convenience. Even potentially supportive new evidence will not necessarily justify interlocutory appellate intervention where the claimed harm can be compensated financially.

For developers, option holders, and litigation counsel, the ruling also illustrates the importance of acting promptly when requesting emergency relief and of demonstrating concrete, noncompensable harm. The Court’s expectation of advance notice offers a practical safeguard without freezing the company’s apartment sales.

✉️ Get tomorrow’s cases before your first coffee
Daily Case Law is our free morning digest — the most substantive new decisions, filtered to your jurisdictions and topics, each linking back here for the full analysis.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top