400 Peel Pty Ltd v Tamworth Regional Council — Court upheld appeal and approved accessibility works

Case
400 Peel Pty Ltd v Tamworth Regional Council
Court
Land and Environment Court of New South Wales (Australia)
Judge
Alison Starr (of New South Wales, 2025)
Date Decided
3 November 2026
Citation
[2026] NSWLEC 1730
Topics
development consent, heritage, disability access, conciliation

Background

400 Peel Pty Ltd sought approval for alterations to the locally heritage-listed former National Australia Bank building at 400–402 Peel Street, Tamworth. The proposal included a new ground-floor accessible entry door and awning, a passenger lift, bathroom refurbishment, and associated internal works.

Tamworth Regional Council refused DA2024-0423 on 24 November 2025. The applicant commenced a Class 1 appeal and, following a conciliation conference under s 34 of the Land and Environment Court Act 1979 (NSW), the parties agreed to amended plans and supporting access, structural, electrical and waterproofing material.

The Court’s Holding

Acting Commissioner Starr held that the parties’ agreed outcome was one the Court could make in the proper exercise of its functions under s 34(3). The Court was satisfied that the amended application addressed the relevant planning and procedural requirements, including permissibility in the E2 Commercial Centre zone, heritage considerations, essential services, and the Council’s outstanding contentions.

The Court therefore upheld the appeal and granted development consent for the amended proposal, subject to the conditions in Annexure A. It also ordered the applicant to pay the Council $1,500 in costs thrown away by the amendment, under s 8.15(3) of the Environmental Planning and Assessment Act 1979 (NSW). The Commissioner noted that the Court was giving effect to the parties’ agreement and had not undertaken a discretionary merits assessment under s 4.15.

Key Takeaways

  • A conciliated agreement may be made into orders if it is a decision the Court could properly make under s 34(3).
  • Amended plans and technical evidence resolved concerns about access, structural adequacy, electrical work, waterproofing and heritage impacts.
  • Amending a development application can attract costs for work rendered unnecessary by the amendment.

Why It Matters

The decision illustrates the Land and Environment Court’s role in Class 1 conciliation matters: it must independently confirm jurisdictional requirements before formalising an agreed planning outcome.

For heritage-listed commercial buildings, the case also shows how detailed amended documentation can support accessibility upgrades while addressing heritage and building-compliance issues.

✉️ Get tomorrow’s cases before your first coffee
Daily Case Law is our free morning digest — the most substantive new decisions, filtered to your jurisdictions and topics, each linking back here for the full analysis.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top