Onix Incorporadora Ltda. — Fourth Panel rejected clarification motions and left the internal-appeal ruling intact

Case
Onix Incorporadora Ltda. v. Respondent Not Identified in the Opinion Text
Court
Superior Tribunal de Justiça, Fourth Panel (Brazil)
Date Decided
June 30, 2026
Citation
REsp 2258442
Topics
Clarification Motions; Real Estate Delay; Moral Damages; Consumer Law

Background

A property purchaser obtained R$10,000 in moral damages after the developer delivered the unit approximately one year after the contractual grace period expired. The lower courts identified consequences beyond ordinary breach of contract: the delay frustrated the purchaser’s plan to move into the property around the time of his wedding and required him to continue paying rent.

The Superior Tribunal de Justiça partially considered and denied the developer’s special appeal. The Fourth Panel subsequently denied an internal appeal and maintained that disposition, concluding that the award accorded with the court’s case law on substantial delivery delays. Onix Incorporadora Ltda. then filed clarification motions against the panel’s internal-appeal ruling, alleging that it had failed to address a cited comparator decision, AgInt no AREsp 2.120.205/RJ, and had improperly applied STJ Precedent Statement 83.

The Court’s Holding

The Fourth Panel unanimously rejected the clarification motions. It held that the challenged ruling contained no omission, contradiction, obscurity, or material error within Article 1,022 of the 2015 Code of Civil Procedure. Clarification motions cannot be used merely to relitigate issues that the court has already addressed and supported with reasons.

The panel explained that its prior ruling had stated the governing distinction: delay in delivering a property does not by itself establish compensable moral harm, but a substantial delay may support moral damages when the circumstances show an actual nonpecuniary injury. It also distinguished the developer’s comparator, which involved a seven-month delay and treated moral damages as inherent in the delay. Here, the delay lasted approximately one year beyond the grace period and had identified consequences for the purchaser, including disruption of his planned move around his wedding. The cited comparator therefore did not reveal an unresolved omission or justify reconsideration.

Key Takeaways

  • Under Article 1,022, clarification motions are limited to correcting obscurity, contradiction, omission, or material error; they are not a vehicle for a new adjudication of the dispute.
  • A developer’s delay in delivering property does not automatically create moral damages, but a substantial delay accompanied by concrete nonpecuniary consequences may do so.
  • The panel left intact the ruling denying the internal appeal, including the underlying R$10,000 moral-damages award arising from the approximately one-year post-grace-period delay.

Why It Matters

The decision reinforces both a procedural and a substantive boundary. Litigants cannot use clarification motions to obtain reconsideration simply because they disagree with the panel’s reasoning, while property-delivery cases remain dependent on the delay’s duration and its demonstrated effects rather than on breach alone.

For developers and purchasers, the ruling illustrates the kinds of facts that may convert delayed delivery from ordinary contractual nonperformance into compensable moral harm, including prolonged delay, disrupted major life plans, and the continuing need to pay rent.

✉️ Get tomorrow’s cases before your first coffee
Daily Case Law is our free morning digest — the most substantive new decisions, filtered to your jurisdictions and topics, each linking back here for the full analysis.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top