FYI-For Your Information — Court blocks DEA award based on a late quotation modification

Case
FYI-For Your Information, Inc. v. United States
Court
U.S. Court of Federal Claims
Judge
Eleni M. Roumel (Donald J. Trump, 2020)
Date Decided
August 24, 2026
Docket No.
26-cv-0032
Topics
Bid Protests; Late Quotations; Federal Procurement; Injunctive Relief
Source
Read the full opinion

Background

The Drug Enforcement Administration sought Human Capital Support Services through a FAR Subpart 8.4 procurement. FYI-For Your Information, Inc., the incumbent, and C Evans Consulting LLC both received the highest available adjectival ratings. FYI quoted $9,240,633.60, while CEC quoted $9,313,152.00—a difference of 0.78%—but DEA selected CEC after finding that its technical advantages justified the higher price.

Before award, the contracting officer asked CEC to correct an apparent calculation error and required a response by 1:30 p.m. on June 4, 2025. CEC sent its response at 1:01 p.m., but an email-security hold prevented it from reaching the contracting officer’s inbox until 1:48 p.m. FYI challenged DEA’s consideration of that response, the agency’s evaluation of the non-price factors, and its best-value tradeoff.

The Court’s Holding

The court held that CEC’s response was a quotation modification because it changed tables in the quotation to correct a mistake. FAR 52.212-1’s late-is-late rule therefore applied, and receipt—not the time CEC pressed send—controlled. Because the contracting officer received the modification after the deadline, and the government expressly disavowed reliance on the government-control exception, DEA unlawfully considered it. The violation prejudiced FYI because CEC could not have received the award without the modified quotation.

The court rejected FYI’s remaining challenges. DEA acted fairly in requesting a clarification from CEC without allowing FYI to revise its quotation, rationally evaluated the three non-price factors, and adequately explained why CEC’s technical advantages justified paying 0.78% more. The court granted and denied each side’s motion for judgment on the administrative record in part and enjoined DEA from proceeding with the award to CEC to the extent it rested on the late-received modification, while leaving DEA discretion over how otherwise to proceed with the procurement.

Key Takeaways

  • An emailed quotation modification is timely under FAR 52.212-1 only when the agency receives it, not when the contractor sends it.
  • In a FAR Subpart 8.4 procurement, contractors must be treated fairly and impartially, but the FAR Part 15 requirement for equal discussions does not apply unless incorporated.
  • A concise best-value tradeoff can survive review when the broader award record explains the competitors’ technical differences and why they warrant a price premium.

Why It Matters

The decision underscores the strict consequences of electronic-delivery delays in federal procurements. Even when a contractor transmits a correction before the deadline, an agency generally may not consider it if the modification reaches the designated recipient afterward and no exception applies.

The remedy also illustrates the Court of Federal Claims’ tailored approach to procurement injunctions: the court barred reliance on the unlawful modification but did not dictate whether DEA must cancel, reevaluate, or otherwise restructure the procurement.

✉️ Get tomorrow’s cases before your first coffee
Daily Case Law is our free morning digest — the most substantive new decisions, filtered to your jurisdictions and topics, each linking back here for the full analysis.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top