First Tower Loan v. Dumaris — Court restored the loan balance and contractual interest in a default judgment

Case
First Tower Loan, LLC, d/b/a Tower Loan of Winnfield v. DeAngelo Dumaris, a/k/a DeAngelo Devontay Dumaris
Court
Louisiana Court of Appeal, Second Circuit
Judge
Cox; Stephens; Thompson
Date Decided
September 30, 2026
Docket No.
57,126-CA and 57,130-CA (Consolidated Cases)
Topics
Default Judgments; Consumer Loans; Contractual Interest; Nullity
Source
Read the full opinion

Background

DeAngelo Dumaris obtained a consumer loan from First Tower Loan, LLC, financing $1,694.59 at a stated annual percentage rate of 39.42%. After Dumaris stopped making payments, Tower Loan sued for an alleged unpaid balance of $2,524, plus interest at 35.30% annually for one year beginning August 2, 2020, and 18% thereafter.

Dumaris did not respond, and Tower Loan sought a default judgment supported by an affidavit of correctness and a proposed judgment. Without holding a confirmation hearing, the district court altered the proposed judgment by replacing the requested contractual rates with legal interest. Tower Loan later sought annulment after the Second Circuit held in a separate group of Tower Loan cases that the same district court lacked authority to make substantive changes to proposed default judgments without a hearing. The district court denied annulment, and Tower Loan appealed.

The Court’s Holding

The Second Circuit declined to classify the district court’s original actions as fraud or ill practices under Louisiana Code of Civil Procedure article 2004. Tower Loan had not been deprived of a legal right to present its position, and a nullity action could not serve as a substitute for an appeal based on alleged legal error.

Nevertheless, the appellate court held that the district court substantially erred by leaving its altered judgment in place after learning of the controlling appellate decision. Under article 1702, the district court lacked authority to disregard Tower Loan’s affidavit of correctness or substantively revise the proposed default judgment without ordering a hearing. Exercising its authority under article 2164, the Second Circuit amended the judgment to award Tower Loan $2,524, with interest at 35.30% annually for one year beginning August 2, 2020, and 18% thereafter until paid. It affirmed the judgment in all other respects and rendered judgment as amended.

Key Takeaways

  • A court considering a supported motion for default judgment may not unilaterally make substantive changes to the proposed judgment instead of signing it or ordering a hearing under article 1702.
  • Legal error alone does not establish fraud or ill practices permitting annulment under article 2004, particularly when the complaining party retains an opportunity to obtain appellate review.
  • The appellate court restored the $2,524 balance verified by Tower Loan’s affidavit and the requested interest rates, concluding that the rates complied with Louisiana consumer-credit limits.

Why It Matters

The decision reinforces the procedural limits on a trial court’s treatment of documentary default judgments. A judge who questions the requested principal or contractual interest must use the hearing procedure prescribed by article 1702 rather than rewriting the proposed judgment without giving the creditor an opportunity to be heard.

The opinion also distinguishes an appealable legal error from an “ill practice” supporting nullity, while illustrating the appellate court’s power to render the judgment that is just, legal, and proper on the existing record.

✉️ Get tomorrow’s cases before your first coffee