Esch and Hamlet v. Turner & Company — Oklahoma Supreme Court affirms dismissal of drainage-damage claims as untimely

Case
George A. Esch, Jr. and Lynda A. Hamlet v. Turner & Company, Inc. and Chitwood Farms, LLC
Court
Supreme Court of the State of Oklahoma
Judge
Kuehn, V.C.J.
Date Decided
September 29, 2026
Docket No.
123142
Topics
Statute of repose; Construction defects; Contract limitations; Property damage
Source
Read the full opinion

Background

George Esch and Lynda Hamlet bought a lot in the Lake at Chitwood Farms subdivision in Edmond in 2013. They alleged that the developer, Turner & Company, and the lot seller, Chitwood Farms, defectively designed and constructed a drainage and roadway feature known as C1, redirecting stormwater onto their lot and causing erosion and water damage.

The City of Edmond accepted the subdivision’s final plat in April 2009. The plaintiffs sued in May 2019, alleging negligence, breach of contract, and breach of the implied warranty of workmanlike construction. After the plaintiffs rested in a bench trial, the district court sustained the defendants’ demurrer to the evidence and entered judgment for them.

The Court’s Holding

The Oklahoma Supreme Court affirmed. It held that the ten-year repose period in 12 O.S. § 109 runs from substantial completion of the particular improvement alleged to have caused the harm—not from completion of the development as a whole or based on the defendant’s role as developer. An improvement is substantially complete when it is sufficiently finished for the owner or representative to occupy or use it for its intended purpose, even if minor defects remain.

Because the only evidence showed C1 was complete and usable no later than the City Council’s April 13, 2009 acceptance of the final plat, the plaintiffs’ May 2019 tort claims were filed too late. The court further held that the implied-warranty and contract claims were governed by Oklahoma’s five-year contract limitations period. Any breach concerning the lot occurred upon its March 2013 conveyance, and the later correction deed conveying an interest in C1 did not create a new breach. Turner & Company also was not a party to the lot-sale contract.

Key Takeaways

  • Section 109’s ten-year repose period is tied to substantial completion of the injury-causing improvement, not an entire development project.
  • An implied warranty of workmanlike construction claim sounds in contract and is subject to the five-year contract limitations period, not the construction-defect repose statute.
  • A later conveyance involving a collateral property interest does not restart limitations for an earlier alleged breach of a lot-sale contract.

Why It Matters

The decision establishes a functional, improvement-specific test for substantial completion under Oklahoma’s construction-defect statute of repose. Property owners cannot defer the repose period by characterizing a discrete drainage, roadway, or utility feature as part of a larger unfinished development.

It also reinforces that contract claims accrue at breach, rather than when resulting damage is discovered, absent proof of fraudulent concealment sufficient to toll limitations.

✉️ Get tomorrow’s cases before your first coffee
Daily Case Law is our free morning digest — the most substantive new decisions, filtered to your jurisdictions and topics, each linking back here for the full analysis.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top