Show: 1 day 1 week 1 month All
Custom (decided):
Coverage since April 10, 2026
✉️ New decisions, briefed in your inbox every morning — subscribe to Daily Case Law, free →

Construction Law

Appellate Division, Second Department
Uncategorized

Vinson v. Ferrara Bros. — General Contractor’s Summary Judgment Reversed: Supervisory Authority Over Delivery Work Is a Triable Issue

Second Department reverses summary judgment for Toll Brothers developer: general contractor failed to eliminate triable issues of fact as to whether it had supervisory authority over concrete delivery operations — that question must go to trial.

Appellate Division, Second Department
Uncategorized

Matter of Lipsky v. Groundbreakers Contracting — Court Confirms Arbitration Award: Written Submissions Were Sufficient, No Formal Hearing Required

Second Department reverses vacatur of arbitration award in construction subcontract dispute: arbitrator properly resolved the matter on written submissions after parties agreed to a paper-based process — skipping a scheduled conference call did not constitute a failure to hold a required hearing.

Appellate Division, First Department
Uncategorized

Morina v. 250 Broadway Associates Corp. — Scaffold Law § 240(1) Liability Extends to Successor-Merged Owner, Condominium, and Building Manager

The First Department affirms summary judgment for a stone mechanic struck by a 350-pound falling panel, holding that all four defendants — including a post-merger associate, a lobby condominium, and a building manager who contracted for the work — qualify as owners or statutory agents under Labor Law § 240(1).

Appellate Division, Second Department
Uncategorized

Berkley Insurance v. Farm Family Insurance — Subcontractor’s Insurer Must Defend General Contractor Based on Deposition Evidence

Second Department affirms duty to defend general contractor as additional insured where injured worker’s deposition in the underlying action established he was using the subcontractor’s ladder — applying the four corners rule’s exception for formal litigation submissions.

Appellate Division, Second Department
Uncategorized

WDF, Inc. v. A.J. Pegno/Tully Construction (Companion) — Release Ambiguity Bars Summary Judgment for Joint Venture Defendants

In the companion appeal to the WDF v. Pegno construction dispute over a Newtown Creek project liquidating agreement, the Appellate Division, Second Department affirms denial of summary judgment to the joint venture defendants on their release defense, holding that the release clause is ambiguous as to claims arising from the post-execution City settlement.

Appellate Division, Second Department
Uncategorized

WDF, Inc. v. A.J. Pegno/Tully Construction — Release in Construction Liquidating Agreement Is Ambiguous as to Post-Settlement Claims

In companion decisions on cross-appeals, the Appellate Division, Second Department holds that the release clause in a construction subcontract liquidating agreement is ambiguous as to whether it bars claims arising from the joint venture’s post-execution settlement with the City of New York—leaving the scope of the release and the parties’ cooperation obligations for trial.

Court of Appeals of North Carolina
Uncategorized

K. Lee Builders, Inc. v. Barnes — Incorrect Furnishing Dates Render Mechanic’s Lien Fatally Defective

The North Carolina Court of Appeals held that a mechanic’s lien with incorrect (not merely omitted) dates of first and last furnishing is fatally defective under N.C.G.S. § 44A-12, regardless of actual prejudice, and that the cash bond posted to discharge the defective lien must be returned to the property owner even though the contractor prevailed on its breach-of-contract claim at trial.

Uncategorized

Bohannon v. Martin McDonald Development — Ninth Circuit Clarifies That Doe Substitution Under CCP § 474 Can Survive California’s 10-Year Construction Repose Period

The Ninth Circuit holds that California’s 10-year construction statute of repose (CCP § 337.15) cannot be extended by equitable tolling to correct a misnamed party, but can be harmonized with CCP § 474’s Doe-substitution mechanism — allowing plaintiffs who timely named unknown contractor

Appellate Division, First Department
Uncategorized

Bunay v. One City Block, LLC — First Department Upholds Denial of Scaffold Law Summary Judgment Where Foreman’s Instructions Raised Recalcitrant-Worker Issue

The Appellate Division, First Department affirmed denial of a construction worker’s partial summary judgment on Labor Law §§ 240(1) and 241(6) Scaffold Law claims, finding the foreman’s testimony that plaintiff was instructed to use a scissor lift — not a ladder — created a triable recalcitrant-worker defense.

Appellate Division, First Department
Uncategorized

Tekton Bldrs., LLC v. 1232 S. Blvd LLC — First Dept. Affirms Lien Dismissal for Willful Exaggeration but Denies Conditions-Precedent Defense

The First Department affirmed summary judgment dismissing a contractor’s mechanic’s lien foreclosure claim under New York’s Lien Law willful exaggeration defense after the contractor admitted including over $1 million for work never performed, but denied summary judgment on the owner’s conditions-precedent defense because the parties’ course of conduct raised factual issues about whether notice requirements were waived.

Uncategorized

Fazel v. Pete Fowler Construction Services — Litigation Privilege Bars Negligence Suit Against Expert for Defective Repair Recommendations

California’s Fourth Appellate District held that California’s absolute litigation privilege bars a property owner from suing an opposing construction expert for negligence in formulating repair recommendations contained in a litigation expert report, even after those repairs failed.

Appellate Division, Second Department
Uncategorized

Neto v. Buddies Bro — Scaffold Law Summary Judgment Reversed Where Plaintiff Bypassed Provided Ladder

The Appellate Division, Second Department reversed a plaintiff’s Labor Law § 240(1) summary judgment after defendants raised a triable issue of fact on the sole-proximate-cause defense, showing that a six-foot ladder was available but that the carpenter chose to use scissor clamps on a cement column instead.

Appellate Division, First Department
Uncategorized

Woodward v. J.T. Magen — Labor Law § 241(6) Passageway Claim Revived; Integral-to-Work Doctrine Rejected

First Department reinstates a Labor Law § 241(6) claim for a worker who tripped on a floor inlay in a corridor after finding genuine fact issues on whether the space was a ‘passageway’ under the Industrial Code, and holds the integral-to-work doctrine inapplicable absent evidence of active work on the hazard.

Appellate Division, Second Department
Uncategorized

Concrete Structures v. Armory Builder III — Arbitration Award for Wrongfully Terminated COVID Shutdown Subcontractor Confirmed

The Appellate Division, Second Department affirms confirmation of a $1.09 million FAA arbitration award in favor of a concrete subcontractor wrongfully terminated during the COVID-19 construction shutdown, rejecting the general contractor’s argument that the panel’s ruling manifestly disregarded the law.

Appellate Division, Second Department
Uncategorized

Herrera v. City of New York — Triable Issue Preserved on Labor Law § 240(1) Where Backhoe Load Moved Under Force of Gravity

The Appellate Division, Second Department affirms denial of summary judgment on a Labor Law § 240(1) Scaffold Law claim where conflicting testimony created a triable issue of fact as to whether a worker was struck by a suspended load moving under the force of gravity when a backhoe’s tire entered a depression in the roadway.

Texas Court of Appeals, Seventh District (Amarillo)
Uncategorized

Martignoni v. Artistry Homes — Homebuyers Lose Summary Judgment Fight After Failing to Preserve Evidentiary Objections

The Seventh Court of Appeals affirmed no-evidence summary judgment against homebuyers who contracted for a $600,000 custom home, holding that their failure to respond to the builder’s evidentiary objections in the trial court forfeited those challenges on appeal under the preservation rule — leaving them without sufficient evidence to withstand summary judgment on any claim.

Appellate Division, First Department
Uncategorized

Sinera v. Bedford-Webster — Floor Collapse Supports Labor Law §§ 241(6) and 200 Liability; Full Contractual Indemnification Awarded Against GC

The First Department upheld Labor Law §241(6) and §200 liability arising from a Bronx building floor collapse caused by stored-material overloading, and modified the order to award full contractual indemnification against the general contractor.

Appellate Division, First Department
Uncategorized

Matter of Broadway PT 1710 v. Kingdom Assoc. — Lien Law § 19(6) Summary Discharge Requires Facial Defect, Not Merits Challenge

The First Department reversed summary discharge of a mechanic’s lien, holding that Lien Law § 19(6) authorizes discharge only for facial defects in the notice of lien—substantive validity challenges belong in a foreclosure action, not a summary discharge proceeding.

Scroll to Top