Great Smoky Mountains R.R. v. Mach 2 Invs. — Third Parties Cannot Attack a Railroad’s Deed from NCDOT, Even If State Conveyance Procedures Were Not Followed

The North Carolina Court of Appeals reversed a Rule 12(b)(6) dismissal in a railroad trespass and quiet-title action, holding that Mach 2 Investments and adjoining property owners lacked standing under the jus tertii doctrine to challenge Great Smoky Mountains Railroad’s 1996 deed from NCDOT. Even if the conveyance did not strictly follow state-lands procedures, only the State can mount that challenge—and any defect would render the deed merely voidable, not void. On remand, the trial court must address necessary parties and examine the scope of a historic “farm crossing” easement whose claimed use Mach 2 may have overburdened through subdivision.

North Carolina Court of Appeals
Uncategorized

Daedalus, LLC v. Mecklenburg County — County Cannot Sue for Homeowner Damages, Owners Who Never Pleaded Their Own Claims Lose Damages Award

The North Carolina Court of Appeals vacated a trebled-damages award in a Mecklenburg County building-code enforcement suit, holding that a county lacks standing under Dillon’s Rule to recover monetary damages on behalf of private homeowners and that intervenors who never pleaded their own claims cannot collect from the county’s judgment, while remanding the underlying duplex-vs.-townhouse liability issue for re-evaluation under the 2012 and 2018 code editions that governed at the time of construction.

North Carolina Court of Appeals
Uncategorized

Alston v. Jacox — Prescriptive Easement Over Decades-Old Pathway Upheld Even After Third-Party Permission Grant

The North Carolina Court of Appeals affirmed a prescriptive easement over a rural pathway that had been used for ingress and egress since the 1950s, holding that the required twenty-year period need not immediately precede the dispute and that an easement already vested by adverse use cannot be destroyed by a later permission grant to a third party.